VULCAN 110/20/10KV POWER STATION

August 14, 2018 in ENERGY

VULCAN 110/20/10KV POWER STATION

Civil works included:

  • Replacement of the 110 kV transformer cell lines through the decommissioning of the existing GIS cells; installation and commissioning of a new hybrid equipment
  • Replacement of the neutral treatment groups and the installation of a fault current detection on all MV feeders;
  • Replacement of the 110 kV power transformer and of the 110/10 kV and 20/10 kV cable connection;
  • Replacement of the 110 kV protection panels and MV electrical equipment;
  • Refurbishment of the control room and installation of new LV switchboards and AC and DC control cabinets;

Electrogrup successfully implemented:

  • Project Management – our teams coordinated the entire work;
  • Health and Safety coordination;
  • Primary and secondary 110,20, 0.4 kV equipment installation;
  • SCADA system and commissioning;

Challenges:

  • Working in an operating power station, with underground HV and MV cable and HV equipment
  • Provisionally control circuits and ensuring the consumer`s power supply during the execution of the works