JUCU 110/20KV POWER STATION

August 14, 2018 in ENERGY

JUCU 110/20KV POWER STATION

The renovation and construction works within the existing operating 110kV power station included: replacement of the existing cells, of the relay room, MV switchgear room, LV services and electrical equipment

Civil works included:

  • Refurbishment of the control and connection building;
  • Replacing of the existing foundations;
  • Replacing the concrete old structure with a steel structure;
  • 110 / 20 kV Power Transformer;
  • Site works: yard, access roads, alleys, drainage;

Electrogrup successfully implemented:

  • Project Management – our teams coordinated the entire work;
  • Health and Safety coordination;
  • Primary and secondary 110,20, 0.4 kV equipment installation;
  • SCADA system and commissioning;

Challenges:

  • Working in a live substation with overhead power lines, underground cables and HV equipment;
  • Provisionally control circuits;